5 Toll Roads That Operate on This Month

by Sebastianus Epifany Friday, September 8, 2017 - 15:29

JAKARTA - The Ministry of Public Works and Housing (PUPR) has planned the operation of five toll roads along 97,31 km. Before being officially operated, these five toll road sections have been used to help cope with traffic jams during Lebaran 2017.

Based on the report from pu.go.id (8/9), here are the five toll road segments:

1. Semarang-Solo section III (Bawen-Salatiga) 17,6 km.

The feasible schedule of functions is on 9 to 10 August 2017, certificates worth of operations is on 25 August 2017, the plan for the inauguration of the first week of September, 4-9 September 2017.

2. Kertosono-Mojokerto section II (Jombang-Mojokerto Barat) 19,9 km

The feasible schedule of functions is on 29-30 August 2017, certificates worth of operations on 7 September 2017, the plan of the inauguration is in the third week of September, 18-23 September 2017.

3. Palembang-Indralaya section I (Palembang-Pamulutan) 7,75 km.

The feasible schedule of functions is on 5-6 September 2017, certificates worth of operations September 14, 2017, the inauguration plan is in the third week of September, 18-23 September 2017.

4. Medan-Kualanamu-Tebing Tinggi 41,6 km.

The feasible schedule of functions on 12-23 September 2017, certificates worth of operations is on 14 September 2017, the inauguration plan is in the fourth week of September, 25-30 September 2017.

5. Medan-Binjai section 2 and 3 (Helvetia-Binjai) 10,46 km.

The feasible schedule of functions on 14-15 September 2017, certificates worth of operations is on 22 September 2017, the inauguration plan is in the fourth week of September, 25-30 September 2017.

Meanwhile, at the end of 2017, the PUPR Ministry targets to have additional new toll roads operating for 380 km.

                                                                                                                               